TMH Telecom’s Fiber Project Experience

Routes Distance Category Time Scope
Presidential palace (NayPyiTaw) 260 Line FTTH City FOC project 2010 Row, Full TK
CNPC Mandalay-Ksaukse 50 KM Buried FOC project 2013 Row, Full TK
CNPC Muse-Nankam 36 KM Buried FOC project 2013 Row, Full TK
Ooredoo, Mezali-Pyaopon 210 KM Buried FOC project 2015 Row, Full TK
Ooredoo, Takon-Pinlaung 130 KM Buried FOC project 2015 Row, Full TK
Ooredoo, Paltein-Labltta 142 KM Buried FOC project 2015 Row, Full TK
Ooredoo, Paltein-Chaungthar 77 KM Buried FOC project 2015 Row, Full TK
Ooredoo, Moegaung-Nanyong 290 KM Buried FOC project 2015 Row, Full TK
Eager, Monywa-Nanyun 220 KM Buried FOC project 2015 Row, Full TK
MPT Kyu kole-Pamsai 50 KM Overhead 2016 Row, Full TK
China Unicom Muse City – Ruili China Across the border 15 KM Overhead 2016 Row, Full TK
GT Broadband FTTX Overhead (on going) 500+ KM Overhead 2017 Row, Full TK

Totally 1,220KM Fiber have been successfully delivered